Project References

...

Century Bhavan, Mumbai, India

Project Duration: 2 Years 3 Months

Completed: 2013

  • 20 floor building located at Worli, Mumbai
  • Integrated building automation including HVAC, Plumbing & Electrical Equipment
  • Control and monitoring of over 2,500 Points
  • 101 BACnet Programmable Controllers
  • 3 Network Controller
  • Web-based EC-NetAX system
...

Bank of India, Mumbai

Project Duration: 1 Year 5 Months

Completed: 2013

  • 12 floor head office building is the first of a series of “growth centers” located in Mumbai at Bandra Kurla Complex.
  • Integrated building automation including HVAC, Plumbing, Fire Fighting,& Electrical Equipment.
  • Control and monitoring of over 1,500 Points include Integration
  • 60 BACnet Programmable Controllers
  • 2 Network Controller
  • Web-based EC-NetAX system
...

Ascendas MTBS, Hyderabad, India

Project Duration: 1 Year 3 Months

Completed: 2017

  • 11 floor head office building located in Hyderabad at “V Tech Park” Hitech City.
  • BMS with Life Safety System, CCTV, Networking and ELV System Power Distribution.
  • Integration with HVAC, Elevators, Electrical meters, Plumbing, Fire Fighting,etc.
  • Control and monitoring of over 5,000 Points include Hardwire & High-level Interface
  • 48 BACnet IP Programmable Controllers
  • Web-based EC-NetAX system
  • 6 Loop Fire Alarm Panel with approx. 500 detectors and devices and 250 speakers.
  • NVR based CCTV system with 3 NVRs for 83IP Cameras considering both Dome PoE& PTZ.
  • Integrated Tenant Billing software
...

Country Inn Hotel, Mysore-Karnataka

Project Duration: 8 Months

Completed: 2018

  • Country Inn Hotel Group of Wadhwan situated in Mysore, Karnataka
  • Integrated building automation including HVAC, Plumbing and Electrical Equipment
  • Control and monitoring of over 1,250 Points include Hardwire & High-level Interface
  • 25 BACnet IP Programmable Controllers
  • Web-based EC-NetAX system
  • Chilled Water Plant, Cooling Towers, AHU, CSU, TFA and Exhaust and Fresh Air Fans
  • Electrical System, DG Sets, Lift Integration
  • Utility ... Plumbing, Fire Fighting, ....
...

GOI, Civil Court Karnataka-Dharwad, India

Project Duration: 1 Year 2 Months

Completed: 2018

  • Hubli Court Complex situated in Dharwad, Karnataka
  • Building Management System (BMS) and Access Control System (ACS)
  • BMS consist of –
    • Web-based EC-NetAX system
    • Over 2,500 points for monitoring and control
    • 50 BACnet IP Controllers
    • 40 AHUs, 10 TFA, Chiller Plant, fire fighting and plumbing equipment.
    • High level integration like EM, VFD, DG Set, Chillers, etc.
  • ACS consist of –
    • Access Control Software
    • 52 Door Controllers
...

Cipla Ltd, Unit III & IV Pithampur- Indore

Project Duration: 1 Year 8 Months

Completed: 2011

  • Cipla Pharma Plant located in Pithampur, Indore.
  • Building automation system for HVAC control
  • Control and monitoring of over 20,000 Points
  • More than 400 LonWorks Programmable Controllers
  • 12 Network Controllers
  • Web-based EC-NetAX system
  • 21 CFR Part 11 Compliance Software
  • Special Reports are created for generation of Batch Process & Audit trail
...

Cipla Ltd, Unit II Baddi – Himachal Pradesh

Project Duration: 1 Year 2 Months

Completed: 2013

  • Cipla Pharma Plant located in Baddi, Himachal Pradesh
  • Building automation system for HVAC control
  • Control and monitoring of over 5,000 Points
  • 51 LonWorks Programmable Controllers
  • 8 BACnet IP Controllers
  • 1 Network Controllers
  • Web-based EC-NetAX system
  • 21 CFR Part 11 Compliance Software
  • Special Reports are created for generation of Batch Process & Audit trail
...

Biocon Ltd, Bangalore

Project Duration: 2 Months

Completed: 2017

  • Biocon Pharma Plant located in Bangalore
  • Building automation system for HVAC control
  • Control and monitoring of over 1,250 Points of High-level Interface
  • 13 FAHU and 3 Ventilation fans
  • Web-based EC-NetAX system
  • 21 CFR Part 11 Compliance Software
  • Special Reports are created for generation of Batch Process & Audit trail
...

Reliance Industry Limited – Reliance Mall, Jalandhar Punjab

Project Duration: 1 Year 2 Months

Completed: 2018

  • Reliance Mall located in Jalandhar, Punjab
  • Integrated building automation including HVAC, Plumbing, and Electrical Equipment & Light Control.
  • Control and monitoring of over 2,500 Points include Hardwire & High-level Interface
  • 42 BACnet IP Programmable Controllers
  • Web-based EC-NetAX system
...

Enugu Mall, Nigeria

Project Duration: 1 Year

Completed: 2018

  • International Standard Mall with more than 30 Shops, 8 Screen Multiplex, drivethrough Hypermarket, Park and Shop Facility, Banquet hall etc. located in Lagos- Nigeria.
  • Integrated building automation including HVAC, Plumbing, Fire Fighting, Electrical, Fire Alarm and Parking Management systems
  • Control and monitoring of approx. 5,000 Points include Hardwire & High-level Interface
  • 18 BACnet IP Programmable Controllers
  • Web-based EC-NetAX system
  • Integrated Tenant billing software
...

Bosch Ltd, Nashik

Project Duration: 7 months

Completed: 2017

  • Bosch Plant (Block B-302) located at Satpur MIDC in Nashik
  • Integrated building automation including HVAC Control
  • Control and monitoring of approx. 500 Points include Hardwire & High-level Interface
  • 7 BACnet IP Programmable Controllers
  • Web-based EC-NetAX system